• Lock-Tile must be site conditioned at room temperature for 24 hours prior to installation. During this period room temperature should be maintained at 70o F +/- 5o F (21o C +/- 3o C).
  • Remove as much equipment as possible from the work area. Lock-Tile should be laid around rather than under heavy machinery.
  • Thoroughly sweep floor area and remove any debris.
  • Fill any significant holes or cracks.